schema_version: "1"
id: a0bdd860dc3dd2de92e60c7164662242d10d4a483101dbe1b39763f8b543e597
title: Upcoming Process Changes
collection: mulesoft
version: current
locale: en-us
portal_url: https://docs.salesforce.com/mulesoft/current/en-us/rpa-manager/processoperations-upcomingprocesschanges.md
canonical_url: https://docs.mulesoft.com/rpa-manager/processoperations-upcomingprocesschanges
source_site: docs.mulesoft.com
content_type: documentation
content_hash: 4f86929c8279602d7e4749f7989b75dcd70d31c6fa7e9607c30e3bde7ec6ec22
description: MuleSoft Documentation Site
latest: true
---
---
product: RPA Manager
---

# Upcoming Process Changes

> For the full documentation index, see: https://docs.mulesoft.com/llms.txt

The activity library of RPA Builder enables RPA developers to save activities that can be reused in
different processes, such as login procedures or the creation of data sets. To reuse a saved
activity, an RPA developer can import a reference to this activity into a bot task. To reuse a saved
activity, an RPA developer can import a reference to this activity into a bot task.

If an RPA developer edits a referenced activity, RPA Manager shows a label with the number of
changed activities next to the navigation items **Process Operations** and **Upcoming Process
Changes**.

The **Upcoming Process Changes** shows which processes contain the changed activities and enables
you to deploy the latest version.

## Before You Begin

- Ask an organization administrator in Access Management to assign you the required permissions:

  <table><colgroup><col> <col> <col></colgroup><thead><tr><th>Action</th><th>RPA Permission</th><th>Deprecated RPA Permission</th></tr></thead><tbody><tr><td><p>Open the <strong>Upcoming Process Changes</strong> view of the <strong>Process Operations</strong> module and view the changes.</p></td><td><p>RPA Operations Manager, RPA Administrator</p></td><td><p>Upcoming Process Changes Open</p></td></tr><tr><td><p>Deploy upcoming process changes.</p></td><td><p>RPA Operations Manager, RPA Administrator</p></td><td><p>Upcoming Process Changes Administration</p></td></tr></tbody></table>

- To deploy a process change, the project must be in the design, build, or test phase.

## View Upcoming Process Changes

When an RPA developer edits a deployed activity in the activity library in RPA Builder, a label with
the number of affected instances shows next to the **Process Operations** or **Upcoming Process
Changes** navigation entry.

To view the changes:

1.  Open the **Upcoming Process Changes** view in the **Process Operations** module.

2.  View the descriptions in the table.

3.  Click **Show Changes** (![eye symbol](/mulesoft/current/en-us/rpa-manager/_images/show-icon.png)) in the row of the edited activity
    to compare the deployed version with the latest version of that activity.

## Map BPMN Elements to Process Activities

If a process contains the same activity more than once, use your browser’s developer tools to find
out which BPMN element contains the referenced activity revision:

1.  Open the **Upcoming Process Changes** view in the **Process Operations** module.

2.  Right-click on a process name and open the project in another tab.

3.  In the new tab, open the **Automation** panel.

4.  Right-click on one of the possible activities and choose **Inspect** from the browser’s context
    menu.

The **Elements** panel of the browser shows the highlighted source code of the element.

To map this element to an element shown in the **Upcoming Process Changes** table:

1.  In the **Elements** panel, look up the text next to **data-element-id=** contained in the source
    code belonging to the highlighted text.

2.  Switch back to the **Upcoming Process Changes** tab.

3.  Compare the **data-element-id** with the **BPMN Element** id in the list of all process changes.

Matching activities have the same id.

![Screenshots of the Upcoming Process Changes table and the Automation Panel’s developer tools elements view with an element highlighted. An arrow shows matching IDs.](/mulesoft/current/en-us/rpa-manager/_images/rpa_processOperations_UpcomingProcessChanges_WhichBPMNElement.png)

## Deploy the Latest Version of an Activity

To ensure that the processes use an appropriate version of a referenced activity, deploy the latest
version to processes in the design, build, or test phase.

Before you deploy the latest version of an activity:

- [View the upcoming process changes](#view-upcoming-process-changes).

- If a process contains the same activity more than once,
  [ensure that you know which activity to select](#map-bpmn-elements-to-process-activities).

- If processes containing an upcoming change are in the produtcion phase, transfer the processes to
  the test phase to deploy the changed activity.

To deploy the latest version of an activity:

1.  Open the **Upcoming Process Changes** view in the **Process Operations** module.

2.  Select the activities to deploy.

3.  Click **Deploy**.

Test the updated processes before transfering them to production phase.

## Deploy An Earlier Version of an Activity

To ensure that a process uses an appropriate version of a referenced activity or to undo a prior
deployment, change the version of a referenced activity in RPA Builder:

1.  Transfer the process to the build phase.

2.  Open the process in RPA Builder.

3.  [Change the revision of the referenced activity using RPA Builder](https://docs.mulesoft.com/rpa-builder/latest/activity-library#change-the-revision-of-a-referenced-activity).

4.  Upload the process to RPA Manager.

5.  Transfer the process to the next phase.

Test the updated process before transferring it to the production phase.

## See Also

- [RPA Builder: Activity Library Explorer](https://docs.mulesoft.com/rpa-builder/latest/activity-library-explorer)