For the managed package runtime, before you can create calculation procedure steps, you must configure the calculation procedure as a whole.
This information is for Omnistudio for Managed Packages. For Omnistudio on standard runtime, see Omnistudio Help.
- On the Vlocity Calculation Procedures list page, click New.
- Enter a Calculation Procedure Name, then click Save.
- In the Vlocity Calculation Procedure Versions list, click the name of the version you just created.
-
To complete the header, click Edit.
In the Vlocity Calculation Procedure Version Detail header, enter the following information:
-
Start Date Time: The day and time Vlocity will start using this calculation procedure.
-
End Date Time: The day and time Vlocity will stop using this calculation procedure.
-
Enabled: Select to enable this calculation procedure and locks it. Note: You can't edit a calculation procedure that's enabled.
-
Priority: The priority Vlocity gives this calculation procedure if a call matches more than one enabled calculation procedure. The higher the priority number, the higher Vlocity ranks it. For example, if Vlocity finds two matching calculation procedures, RatingCalc with Priority = 1 and RatingCalc with Priority = 2, Vlocity uses the calculation procedure with Priority = 2.
-
Version Number: Change if you want to give this calculation procedure a different version number.
-
Enable Looping: Select to enable this as a looping calculation procedure.
To learn more about looping calculation procedures, see Using Looping in Calculation Procedures.
-
Looping Specification: If you selected Enable Looping, enter a looping specification here.
-
- Click Save.