This job populates Requested Start datetimes from old Request dates for each order.
|
Applies to |
Upgrades from Salesforce Industries Communications, Media, and Energy v15 release |
|---|---|
|
Apex Name |
PopulateRequestedStartDateBatchJob |
|
Where to Run this Job |
Upgrade Jobs link on the CMT Administration tab. |
|
Risks of Running This Job |
Low Risk. This job populates the new Requested Start Date field that is the new date field for submission of an order. |
|
When Not to Run This Job |
N/A |
|
When to Run This Job |
When upgrading to v.103.x or later releases. During the upgrade, this job populates the new Requested Start Date field with values from the old Request Date field. |
|
More Information |
The FDO orders from v103 will now use the requested start date field, which is a date time field for submit orders. |