schema_version: "1"
id: 31caa3cbb879c4b4bc8c2c5b712b7c710803124e5b2300db2efd4e7058047430
title: Amend In-Flight Orders in LWC
collection: admin
version: current
locale: en-us
portal_url: https://docs.salesforce.com/admin/current/en-us/ind/264-0-0/comms_amend_in_flight_orders_in_lwc.md
canonical_url: https://help.salesforce.com/s/articleView?id=ind.comms_amend_in_flight_orders_in_lwc.htm&release=264.0.0&type=5
source_site: help.salesforce.com
content_type: documentation
content_hash: 233daea53930724fb9471980eef8b19c9bca3c0706a0de2597686e9f3f77a7c6
description: Any order that is in the process of fulfillment is referred to as an In-flight order. Using the Amending In-Flight Orders feature, you can modify your order after you've submitted it. It helps you fine-tune your order before order management completes its fulfillment.
products:
  - Communications
  - Media
  - Energy and Utilities
release: "264"
---
# Amend In-Flight Orders in LWC

Any order that is in the process of fulfillment is referred to as an In-flight order. Using the Amending In-Flight Orders feature, you can modify your order after you've submitted it. It helps you fine-tune your order before order management completes its fulfillment.

1. From the App Launcher, search for **Orders** and open it.
2. From the orders list, open an order to amend.
    
    The order must be submitted and in the in-progress state.
3. In the tab for the order, select **Amend** from the menu.
    
    You can also select **Amend** from the Industries Cart for the order.
    
    ![Order status](https://sf-zdocs-cdn-prod.zoominsoftware.com/tdta-ind-comms_media_energy_managed-264-0-0-production-enus/ff4079f6-a384-475c-b863-578bbbb0ef9b/resources-product/images/cpq__lwc__inflight_amend.png)
    
    CPQ creates a supplemental order with the order status set to **Ready to Submit**. The original order status changes to Amend Requested.
4. Add, modify, or delete the cart line items. You can also modify, add, or cancel a promotion and discount that applies to a line item.
    
    You can modify a line item only if it hasn't passed the point of no return (PONR). PONR is a state in the order fulfillment process after which you can't modify an order, including a promotion or discount that applies.
    
    See [In-Flight Amendments](https://help.salesforce.com/s/articleView?id=ind.comms_t_in_flight_amendments_183332.htm&release=264.0.0&type=5 "After you submit an order, you can cancel or modify it. But it must have a status of in-progress, and it can't be past the point of no return (PONR). If Order Management (OM) has fulfilled the order, you can amend the order by creating a follow-on order and submit the changes to be queued until OM fulfills the original order.").
    
    ![Note](https://sf-zdocs-cdn-prod.zoominsoftware.com/tdta-ind-comms_media_energy_managed-264-0-0-production-enus/ff4079f6-a384-475c-b863-578bbbb0ef9b/images/icon_note.png)
    
    Note
    
    After you complete amending the supplemental order, you can also discard the changes before you submit the order for fulfillment.
    
    To discard the changes you made to the order, from the cart actions, click the arrow and then click **Delete**. CPQ discards the supplemental order and the original order is activated for order fulfillment. See [Order Statuses in CPQ](https://help.salesforce.com/s/articleView?id=ind.comms_order_statuses_in_cpq.htm&release=264.0.0&type=5 "In Industries CPQ, an order changes status several times before order management processes and fulfills the order. The following table lists the available order statuses in Industries CPQ.").
5. When you complete amending the supplemental order, click **Submit Order**.
    
    The shows the original carts items with an Existing while, and new items have a New status.
    
    ![New and Existing Status](https://sf-zdocs-cdn-prod.zoominsoftware.com/tdta-ind-comms_media_energy_managed-264-0-0-production-enus/ff4079f6-a384-475c-b863-578bbbb0ef9b/resources-product/images/cpq__lwc__inflight_amended_order.png)
    
    After you submit an amended order, the following status changes occur on the supplemental and the original orders:
    
    - OM accepts the order: The supplemental order status changes to In-Progress and the original order is superseded.
    - OM rejects the order: The supplemental order is rejected and the original order is activated.
    
    ![Note](https://sf-zdocs-cdn-prod.zoominsoftware.com/tdta-ind-comms_media_energy_managed-264-0-0-production-enus/ff4079f6-a384-475c-b863-578bbbb0ef9b/images/icon_note.png)
    
    Note
    
    If the order is a follow-on order, the order is queued until the original order is fulfilled by OM. See [In-Flight Amendment: Changing the Default Behavior of a Running Order Item](https://help.salesforce.com/s/articleView?id=ind.comms_t_in_flight_amendmentchanging_the_default_behavior_of_a_running_orderitem_234637.htm&language=en_US).

See Also:

- [Cancel an In-Flight Order in LWC](https://help.salesforce.com/s/articleView?id=ind.comms_cancel_an_in_flight_order_in_lwc.htm&language=en_US)
- [View Status Notifications for In-Flight Orders](https://help.salesforce.com/s/articleView?id=ind.comms_view_status_notifications_for_in_flight_orders.htm&language=en_US)
- [View Amendment History for In-Flight Orders in LWC](https://help.salesforce.com/s/articleView?id=ind.comms_view_amendment_history_for_in_flight_orders_in_lwc.htm&language=en_US)